Set up properties for operations resources

Important

This content is archived and is not being updated. For the latest documentation, see Microsoft Dynamics 365 product documentation. For the latest release plans, see Dynamics 365 and Microsoft Power Platform release plans.

Applies To: Microsoft Dynamics AX 2012 R3, Microsoft Dynamics AX 2012 R2, Microsoft Dynamics AX 2012 Feature Pack, Microsoft Dynamics AX 2012

Operations resource properties are special attributes that you can assign to your resources for use in the scheduling process. Properties that you set up can be assigned to working time templates in the Working time templates form. For more information, see Working time templates (form).

Note

Resource properties are not required when you set up Working times calendars. However, if you want to use properties, it is more efficient to set them up at the same time.

  1. Click Production control > Setup > Resources > Properties.

  2. Press CTRL+N to create a new line.

  3. In the Property field, enter an alphanumeric identifier for the property.

  4. In the Name field, enter the name of the property.

  5. Click Values.

  6. In the Name field, enter the name that you assigned to the property in step 4.

  7. In the Value field, enter any additional information about the property.

See also

Create working time templates

Create working time calendars

Properties (form)