PidLidTaskEstimatedEffort Canonical Property
Applies to: Outlook 2013 | Outlook 2016
Indicates the amount of time, in minutes, that the user expects to perform a task.
Property | Value |
---|---|
Associated properties: |
dispidTaskEstimatedEffort |
Property set: |
PSETID_Task |
Long ID (LID): |
0x00008111 |
Data type: |
PT_LONG |
Area: |
Task |
Remarks
The value must be greater than or equal to 0 and less than 0x5AE980DF (1,525,252,319), where 480 minutes equal one day and 2400 minutes equal one week (eight hours in a work day and five days in a work week).