This article describes how to create a simple workflow by using SharePoint Designer 2013. You can export the workflow to Visio 2013 for visualization and editing, or use Visio 2013 to design Project Server 2013 workflows and import the design into SharePoint Designer 2013 for publication to Project Web App. For more information about the SharePoint workflow platform and creating workflows with Visio 2013 and SharePoint Designer 2013, see the Workflows in SharePoint 2013 articles in the SharePoint 2013 developer documentation.

For information about preparing Project Server for workflows, see Start: Set up and configure SharePoint 2013 Workflow Manager.

Creating a general workflow

Use the following steps to create a Project Server 2013 workflow by using SharePoint Designer 2013. The workflow is designed for demand management of project proposals.

For detailed steps, see the Creating a branching workflow section.

To create a Project Server workflow (general procedure)

  1. Determine the requirements, and then design the workflow. Organize it into phases and stages, and determine the custom fields that the workflow will use.

  2. In Project Web App, create the entities that the workflow requires:

    1. Review the existing workflow phases; create phases as necessary.

    2. Create the enterprise custom fields that the workflow will use. To be available in a workflow stage, a custom field must be controlled by a workflow.

    3. Edit or create the project detail pages (PDPs) that your workflow stages will use to collect information for the project. In this example, the stages use default PDPs that are edited to include a new custom field.

    4. Create the necessary workflow stages, and then associate each workflow stage with the correct phase.

  3. In SharePoint Designer 2013, construct the workflow by using declarative statements in the Text-Based Designer:

    Note

    You can also switch to the Visual Designer in SharePoint Designer 2013, or import an existing workflow from Visio 2013. Follow these steps to use the Text-Based Designer:

    1. Open the Project Web App site, and then create a site workflow that uses the SharePoint 2013 Workflow - Project Server workflow platform.
    2. Add the stages that the workflow uses.
    3. Insert the workflow steps, conditions, actions, and loops that are required in each stage.
    4. Check for any workflow errors and fix any that you find.
    5. (Optional) Switch the view to the Visual Designer, or export the workflow to a Visio 2013 file. You can modify the Visio view and save changes to the current workflow. You can edit the Visio file and import it in SharePoint Designer 2013 to create other workflows.
    6. Publish the workflow. After it is published, the workflow shows in the list of workflows for the Project Web App site.
  4. In Project Web App, use the workflow for demand management of project proposals:

    1. Create an enterprise project template (EPT) that uses the workflow.

    2. On the Project Center page, create a project that uses the EPT for the workflow, and then follow through the workflow stages.

    3. Test the workflow thoroughly.

    4. Deploy the workflow to a production server.

Creating a branching workflow

Before you can use SharePoint Designer 2013 to create a Project Server workflow, the Workflow Manager Client 1.0 service must be configured to use the Project Server 2013 workflow activities. For information about how to configure Workflow Manager Client 1.0, see the Workflows in SharePoint 2013 articles in the SharePoint Server 2013 developer documentation.

The following detailed procedure includes the same steps as in the Creating a general workflow section.

To create a Project Server branching workflow (detailed procedure)

1. Plan and design the workflow

A Project Server workflow can integrate with multiple stages and phases in a demand-management process. Because workflows can be complex, you must understand the business requirements and plan a workflow carefully. For a simple example, design a branching workflow that uses the estimated cost of a project proposal to determine whether the proposal is accepted. If the estimated cost is greater than $25,000 USD, reject the proposal; otherwise, accept the proposal and create the project.

Because you can use Visio 2013 and SharePoint Designer 2013 to help design and create workflows for Project Server 2013, you can more easily experiment with workflows than is possible with Project Server 2010. The sample workflow design in this article is the same as in the Create a branching workflow article in the Project 2010 SDK. You can design and create a test workflow on a remote computer using a test instance of Project Web App—you do not have to create workflows directly on a Project Server 2013 computer.

2. Create the entities that your workflow requires

In Project Web App, review the available workflow phases and stages, and the enterprise custom fields that are available. If necessary, create the entities that your workflow requires, as in the following steps:

  1. Workflow phases The default installation of Project Web App includes the Create, Select, Plan, Manage, and Finished phases. For the branching workflow example, you do not have to create other phases.

  2. Enterprise custom fields The branching workflow requires a project cost custom field that is workflow-controlled. The value of a workflow-controlled custom field is set in a PDP that the workflow uses. For example, choose the Settings icon at the top-right of a Project Web App page, choose PWA Settings, and then choose Enterprise Custom Fields and Lookup Tables.

    Create a custom field named Proposal Cost for the Project entity, and select the type Cost. For the description, type Estimated cost of a project proposal. In the Behavior section, choose Behavior controlled by workflow.

  3. Project detail pages Edit or create the PDPs that the workflow stages will use. For example, do the following steps:

    1. Choose Project Detail Pages on the Server Settings page, and then choose the ProjectInformation PDP.

    2. On the PAGE tab of the ribbon, in the Edit group, choose Edit Page.

    3. Choose the down arrow at the top-right of the Basic Info web part, and then choose Edit web part. Or, on the WEB PART tab of the ribbon, in the Properties group, choose web part Properties to show the editor part.

    4. In the Displayed Project Fields section of the editor part (see Figure 1), choose Modify.

    5. Add the Proposal Cost custom field, move it above the Owner field in the Selected Project Fields list, and then choose OK (see Figure 1).

    6. In the editor part, choose OK, and then choose Stop Editing in the Edit group, on the PAGE tab of the ribbon. Figure 2 shows the Proposal Cost custom field that is added to the Project Information PDP.

    Figure 1. Editing the Project Fields web part in a PDP

    Editing the Project Fields web part in a PDP

    Figure 2. The edited PDP includes the Proposal Cost custom field

    The edited PDP includes the Proposal Cost field

  4. Workflow stages Create the stages that are required for each phase of the workflow. On the Server Settings page, choose Workflow Stages, and then choose NEW WORKFLOW STAGE. Figure 3 shows part of the Add Workflow Stage page.

    Figure 3. Adding a workflow stage in Project Web App

    Adding a workflow stage in Project Web App

    The branching workflow example uses the four stages that are shown in Table 1. In the Additional Settings for the Visible Project Detail Page section of the Add Workflow Stage page (not shown in Figure 3), values are optional; they provide more information on the Workflow Status page. For example, because the Initial Proposal Details PDP requires user input, you can select the The Project Detail Page requires attention check box, and then add a specific description such as Set the project name and cost for this PDP.

    Figure 4 shows the four stages completed on the Workflow Stages page.

    Table 1. Stages for the branching workflow

    Name Description Description for Submit Phase Visible PDPs Custom Fields
    Initial Proposal Details
    Set the project name and cost. Submit the project as a proposal. Create
    Project Information
    Project Details
    Proposal Cost (required)
    Project Details
    Provide details of the proposed project. Submit details to continue with the project. Create
    Project Information
    Project Details
    Proposal Cost (read-only)
    Automated Rejection
    The proposal is rejected, based on the information that is provided.
    Create
    Project Information
    Proposal Cost (read-only)
    Execution
    The proposal is accepted, and ready for project management.
    Manage
    Project Information
    Project Details
    Proposal Cost (read-only)

    Figure 4. List of the workflow stages in Project Web App

    List of the workflow stages in Project Web App

3. Construct the workflow in the Text-Based Designer

In SharePoint Designer 2013, construct the workflow by using declarative statements in the Text-Based Designer. You can start typing at the orange insertion line to get context-sensitive auto-completion statements for the workflow logic and steps, or you can insert the logic and steps by using controls in the Insert group on the WORKFLOW tab of the ribbon.

  1. In the Backstage view of SharePoint Designer 2013, choose Open Site. For example, open https://ServerName/pwa. In the Navigation pane, choose Workflows. Then, on the WORKFLOWS tab of the ribbon, in the New group, choose Site Workflow. For this example, name the workflow Branching Workflow. Ensure that SharePoint 2013 Workflow - Project Server is selected in the Platform Type drop-down list (see Figure 5).

    Figure 5. Creating a Project Server site workflow

    Creating a Project Server site workflow

  2. Select the Branching Workflow tab. Then, on the WORKFLOW tab of the ribbon, in the Manage group, in the Views drop-down list, choose Text-Based Designer. To show the view with the blinking orange insertion line (see Figure 6), click within the view.

    Figure 6. Using the Text-Based Designer view for the workflow

    Using the Text-Based Designer view

  3. In the Text-Based Designer view, add the stages that the workflow uses. On the WORKFLOW tab of the ribbon, in the Insert group, in the Stage drop-down list under Create, choose Initial Proposal Details.

    Similarly, place the orange insertion line below the Stage: Initial Proposal Details box, and add the other stages that the workflow uses: Project Details, Automated Rejection, and Execution (see Figure 7).

    Figure 7. Adding a stage to a workflow in SharePoint Designer

    Adding a stage to a workflow in SPD

  4. Add the workflow steps and logic within each stage:

    1. In the Initial Proposal Details stage, place the orange insertion line at the top of the stage body. In the Insert group on the ribbon, choose Action, scroll down to Project Web App Actions, and then choose Wait for Project Event. Choose this project event, and then select Event: When a project is submitted in the drop-down list.

    2. In the Transition to stage section of the Initial Proposal Details stage, insert If any value equals value. You can start typing the statement or use the Condition control in the Insert group on the ribbon.

    3. Choose the first value control, and then choose fx to show the Define Workflow Lookup dialog box (see Figure 8). In the Data source drop-down list, select Project Data. In the Field from source drop-down list, select Proposal Cost.

      Figure 8. Defining a lookup value in the workflow

      Defining a lookup value in the workflow

    4. Complete the If statement so that it shows the following: If Project Data:Proposal Cost is greater than 25000

      Note

      Alternately, you could create a workflow variable, set the variable to the custom field value, and then compare the variable with a value. For example, from the Local Variables drop-down list on the ribbon, create a variable named TotalCost (no spaces) of type Number. In the Define Workflow Lookup dialog box, select Workflow Variables and Parameters for the data source, and then select Variable: TotalCost as the field. The If statement would then be: If Variable: TotalCost is greater than 25000

    5. Place the orange insertion line within the If branch, and then insert Go to a stage by using the Action control, in the Insert group on the ribbon. Choose the a stage drop-down control and select the Automated Rejection stage.

      Similarly, in the Else branch, insert the Go to Project Details statement. Figure 9 shows the completed Initial Proposal Details stage.

      Figure 9. Completed logic for the Initial Proposal Details stage

      Completed logic for Initial Proposal Details

    6. In the Automated Rejection stage, unless you want to pause the workflow and show some data in a PDP, leave the first section empty. The Transition to stage section must contain a transition; because there is no other stage following a rejection, type Go to End of Workflow for the statement.

    7. In the Project Details stage, add Go to Execution in the Transition to stage section. Unless there is additional data to add, or you want to pause the workflow, it is not necessary to wait for a submitted event.

    8. In the Execution stage, unless you want to pause the workflow, leave the stage action section empty. In the Transition to stage section, add Go to End of Workflow.

  5. In the Save group on the ribbon, choose Check for Errors to check for workflow errors (see Figure 10). Fix any errors, and then choose Save.

    Figure 10. Checking the workflow for errors in SharePoint Designer

    Checking for errors in the workflow

  6. (Optional) In the Manage group on the ribbon, in the Views drop-down menu, choose Visual Designer. In Figure 11, the view is zoomed out to 50%.

    You can edit items in the workflow by using the Visual Designer. For example, select the If any value equals value condition, choose the tool icon at the bottom-left of the condition, and then select Value to show the comparison conditions in the Properties dialog box.

    Figure 11. Using the Visual Designer for a workflow

    Using the Visio design view of the workflow

    When the workflow is in the Visual Designer view, to save the workflow in a Visio 2013 (.vsdx) file as a backup or for later use, you can choose Export to Visio.

  7. Publish the workflow. When you use SharePoint Designer 2013 to publish the workflow to the active Project Web App site, the workflow is registered to the SharePoint site or in Azure and becomes available within Project Web App for new EPTs.

4. Create an EPT for the workflow, and then test the workflow

In Project Web App, create an EPT for the workflow, and then test the workflow by creating a project proposal:

  1. On the PWA Settings page, choose Enterprise Project Types, and then create an EPT named Test Branching Workflow. Clear the Create new projects as SharePoint Tasks List Projects check box so that Project Server will maintain full control of projects that are created by the EPT. Select Branching Workflow in the Site Workflow Association drop-down list, and then select the Project Information PDP in the New Project Page drop-down list to be the first page that the workflow shows.

    Figure 12. Adding an EPT for the workflow

    Adding an EPT for the workflow

    Note

    A Yes value in the SharePoint Tasks List Project column in the table of enterprise project types refers to an EPT that creates a SharePoint tasks list, where the tasks list is visible in Project Web App but SharePoint maintains control of the project. For more information about managing projects as SharePoint tasks lists, see Project Server 2013 architecture.

  2. Open the Projects page in Project Web App, and then create a project by using the new EPT (see Figure 13). Because Test Branching Workflow is associated with Branching Workflow, project creation starts under control of the workflow.

    Figure 13. Creating a project with the Test Branching Workflow EPT

    Creating a project with the EPT

  3. When the workflow displays the Project Information PDP, add data to the project fields. For example, enter a Proposal Cost value of 30000. The U.S. English version of Project Server changes the field to show $30,000 (see Figure 14).

    Figure 14. Using the edited Project Information PDP

    Using the edited Project Information PDP

  4. On the PROJECT tab of the ribbon, in the Project group, choose Save. Project Server adds the data in the PDP to the project, and then shows the Workflow Status page (see Figure 15). To see the full description of the Initial Proposal Details stage in the workflow status diagram, hover the pointer over the stage in the workflow visualization diagram.

    The All Workflow Stages grid uses a green arrow to show that the Initial Proposal Details stage is waiting for input. This is because the workflow waits for a submit event in the Initial Proposal Details stage. If the workflow did not wait for a submit event, you could choose Next in the Page group to advance to the next PDP.

    Figure 15. Using the Workflow Status page in the Initial Proposal Details stage

    Workflow status page after the first stage

    The workflow visualization diagram shows the current stage in a green color. In the Create phase, the Initial Proposal Details stage is the current stage.

  5. On the ribbon, in the Workflow group, choose Submit.

    Tip

    If the Submit control is disabled, refresh the page.

    If the Proposal Cost value is greater than $25,000 USD, the workflow moves to the Automated Rejection stage. Figure 16 shows the Automated Rejection stage status when you choose Submit again. If the Proposal Cost is $25,000 USD or less, the workflow moves to the Project Details stage (see Figure 17).

    Figure 16. The workflow is completed in the Automated Rejection stage

    The workflow is completed in Automated Rejection

    Figure 17 shows another test with a project proposal named Test 2 - Branching, where the Project Details stage is current in the Create phase. The Manage phase shows in a light blue color, which indicates that phase is not yet active.

    Figure 17. The workflow continues to the Project Details stage if the cost is less than $25,000

    Workflow status at the Project Details stage

  6. If you advance to the Project Details stage, there is no additional data to add in the default page. Choose Submit again to advance to the Execution stage (see Figure 18).

    Figure 18. The workflow is ready to manage in the Execution stage

    Workflow status in the Execution stage

In the Project Details stage, the workflow does not wait for a submit event. If the Project Details PDP includes additional required fields, Project Server waits until you add data to the fields before continuing to the Execution stage. As defined in the Branching Workflow, the Execution stage also does not wait for a submit event. In the Execution stage, you can edit the project as a project manager or choose Close in the PROJECT tab of the ribbon. When you choose Close, you can check in the project and edit it later or leave the project checked out.

The Branching Workflow project is a simple example that has only one comparison test. The workflow involves three stages in the Create phase and one stage in the Manage phase of Demand Management. To thoroughly test a workflow, you should test all branches of the workflow and use extreme and typical values to see whether the behavior is as expected.

Importing a workflow from Visio

To change the workflow, you can create or modify workflow-controlled custom fields and create or modify workflow phases and stages. You can use SharePoint Designer 2013 to add conditions, actions, loops, and stages, and then save and republish the workflow. To reuse or keep a backup of a workflow, you can export it to a Visio 2013 file.

You can also create or edit the workflow in Visio 2013 and import the file into SharePoint Designer 2013 for use by Project Web App. To use an unmodified workflow, the Project Web App instance must include workflow stage properties that are the same as those in the original Project Web App instance. For more information about using Visio to help create workflows, see Workflow development in SharePoint Designer 2013 and Visio 2013.

Note

When you import a Visio 2013 file to a different instance of Project Web App, the stages have different stage GUIDs, even if the stage names are the same. After you import the workflow, you must configure the stage and action properties to use values that are specific to the Project Web App instance.

If you create a workflow in Visio 2013, the stages and actions have no properties that are specific for a Project Web App instance because Visio does not connect with Project Web App. When you connect SharePoint Designer 2013 with Project Web App, create a workflow, and then import the VSDX file, you overwrite the active workflow. You must then configure the stage and action properties to match the values that SharePoint Designer 2013 gets from Project Web App.

To import a workflow from Visio to SharePoint Designer

  1. In Visio 2013, create a simple workflow. For example, do the following steps:

    1. Open Visio, and then create a workflow. Choose the CATEGORIES pane for a new workflow, choose Flowchart, choose the Microsoft SharePoint 2013 Workflow template in the New pane, and then choose Create. The workflow opens with a Stage shape named Stage 1. The workflow includes a Start component, and an Enter shape and Exit shape as part of the Stage shape.

      When you hover over the Stage shape and choose the Properties icon, the selection is disabled. You can set the stage and action properties after you import the workflow diagram to SharePoint Designer 2013.

      Note

      The only shape stencils you should use are the following in the list of Flowchart shapes:

      • Actions - SharePoint 2013 Workflow
      • Components - SharePoint 2013 Workflow
      • Conditions - SharePoint 2013 Workflow
    2. In the Shapes pane, choose Quick Shapes, and then drag the Condition shape named If any value equals value to the right of the Stage shape.

    3. On the HOME tab of the ribbon, choose the Connector tool, and then connect the Exit shape on the stage with the Condition shape (see Figure 19).

      Figure 19. Connecting a Stage shape with a Condition shape in a Visio workflow diagram

      Creating a workflow diagram in Visio

    4. Drag two more Stage shapes to the right of the condition shape. The shapes are named Stage 2 and Stage 3.

    5. Using the Connector tool, connect the right side of the Condition shape to the Enter shape of Stage 2. Choose the Pointer tool, double-click the connection to show a textbox for the name, and then name the connection Yes.

    6. Connect the bottom of the Condition shape to the Enter shape of Stage 3. With the Pointer tool, right-click the connection, and then choose No. Either method works for naming the connectors Yes or No.

    7. In the Shapes pane, choose Actions - SharePoint 2013 Workflow, and then drag the Wait for project event action to the middle of the shape for Stage 1 (see Figure 20).

      Figure 20. Completing the workflow in Visio

      Completing the workflow in Visio

    8. On the PROCESS tab of the ribbon, in the Diagram Validation group, choose Check Diagram. Fix any errors, and then save the drawing. For example, name the file Test workflow from Visio.vsdx.

      For information about fixing workflow errors, see Troubleshooting SharePoint Server 2013 workflow validation errors in Visio 2013.

  2. Open SharePoint Designer 2013, and then open the same Project Web App site that you used for the Branching Workflow example.

  3. Choose Workflows in the Navigation pane, and then create a site workflow (choose Site Workflow on the WORKFLOWS tab of the ribbon). For example, name the workflow Simple workflow from Visio.

    In the Create Site Workflow dialog box, ensure that the platform type is SharePoint 2013 Workflow - Project Server. Choose Create, and SharePoint Designer opens the Text-Based Designer pane for the new workflow.

  4. In the Manage group on the WORKFLOW tab of the ribbon, choose Workflow Settings.

  5. In the Manage group on the WORKFLOW SETTINGS tab of the ribbon, choose Import from Visio, and then import the Test workflow from Visio.vsdx file that you previously saved. A Microsoft SharePoint Designer dialog box warns that the diagram you are importing contains no workflow properties, and asks whether to overwrite the current workflow. Choose Yes; SharePoint Designer imports the workflow diagram, generates stencils for the shapes, and displays the Visual Designer pane that contains the imported workflow.

  6. Set the properties of each stage shape in the workflow. For example, the first stage shape is named Stage 1 (Invalid), because it does not represent a valid stage in the connected Project Web App instance. When you select or hover over the stage, you can choose the Properties icon at the lower left of the stage shape to show the Stage Properties dialog box (see Figure 21). Select the Initial Proposal Details stage in the Project Stage drop-down list, and then choose OK. SharePoint Designer renames the stage.

    Figure 21. Setting the stage property in SharePoint Designer

    Setting properties in an imported workflow

    For the second stage, set the Project Stage property to Automated Rejection. For the third stage, set the Project Stage property to Execution.

  7. Similarly, for the Wait for project event action, set the Event Name property to Event: When a project is submitted.

  8. Similarly, set the properties of the If any value equals value condition. For example, set the first Value property to Project Data:Proposal Cost. Set the Operator property to is less than. Set the second Value property to 5000.

  9. Check the workflow for errors, and then save the workflow. If there are no errors, you can change the view to the Text-Based Designer (see Figure 22).

    Figure 22. Viewing the imported workflow in the Text-Based Designer

    Viewing the imported workflow

  10. Publish the workflow. If you save the workflow but do not publish it, the workflow will not be available when you create an enterprise project type.

  11. To test the imported Simple workflow from Visio in Project Web App, create an EPT that uses the workflow, and then create projects that use the new EPT as you did for the Branching Workflow example. In this case, however, projects that are less than $5,000 cost are rejected.

In working through this article, you created and tested a simple branching workflow by using SharePoint Designer 2013 to directly set the stages, conditions, and actions that the workflow uses. You also created a diagram for an even simpler branching workflow by using Visio 2013. You imported the Visio workflow diagram into SharePoint Designer 2013, where you set the properties of each stage, condition, and action from the connection with Project Web App.

Visio 2013 and SharePoint Designer together provide convenient ways for designers, project managers, workflow developers, and testers to create, share, and customize workflow designs for different installations of Project Server 2013 and Project Online. For workflows that require programmatic access to Project Server that SharePoint Designer does not provide, you can use Visual Studio 2012 with the client-side object model (CSOM).