Application.LinkTasks method (Project)
Links the selected tasks in the Gantt Chart, Calendar, Task Sheet, or Task Usage view.
Syntax
expression. LinkTasks
expression A variable that represents an Application object.
Return value
Boolean
Example
The following example a couple of tasks and links them.
Sub Link_Tasks()
'Activate Task Sheet view
ViewApply Name:="Task Sheet"
' Create a coupe of tasks
RowInsert
SetTaskField Field:="Name", Value:="TestTask-2"
SetTaskField Field:="Duration", Value:="5"
RowInsert
SetTaskField Field:="Name", Value:="TestTask-1"
SetTaskField Field:="Duration", Value:="10"
'Select tasks
SelectRow
SelectRow Row:=1, Add:=True
'Link the two tasks
LinkTasks
'delete the tasks
ActiveProject.Tasks("TestTask-1").Delete
ActiveProject.Tasks("TestTask-2").Delete
End Sub