Application.OptionsCalendar method (Project)
Sets options for the calendar of the active project.
Syntax
expression. OptionsCalendar
( _StartWeekOnMonday_
, _StartYearIn_
, _StartTime_
, _FinishTime_
, _HoursPerDay_
, _HoursPerWeek_
, _SetDefaults_
, _StartWeekOn_
, _UseFYStartYear_
, _DaysPerMonth_
)
expression A variable that represents an Application object.
Parameters
Name | Required/Optional | Data type | Description |
---|---|---|---|
StartWeekOnMonday | Optional | Boolean | True if the calendar week starts on Monday. False if the calendar week starts on Sunday. If StartWeekOn is specified, StartWeekOnMonday is ignored. (The StartWeekOn argument is a better way to specify the start of the week.) |
StartYearIn | Optional | Long | The first month of the fiscal year. Can be one of the PjMonth constants. |
StartTime | Optional | Variant | The default start time for working days. |
FinishTime | Optional | Variant | The default finish time for working days. |
HoursPerDay | Optional | Double | The default number of work hours per day. |
HoursPerWeek | Optional | Double | The default number of work hours per week. |
SetDefaults | Optional | Boolean | True if the values of StartYearIn, StartTime, FinishTime, HoursPerDay, HoursPerWeek, StartWeekOn, and UseFYStartYear are used as the default values for new projects. The default value is False. |
StartWeekOn | Optional | Long | The first day of the week. Can be one of the PjWeekday constants. |
UseFYStartYear | Optional | Boolean | True if a fiscal year is determined by the year of the first month of that fiscal year. False if determined by the last month of the fiscal year.For example, if StartYearIn is pjJuly (to denote July 2012) and UseFYStartYear is True, the fiscal year ending in June 2012 would be FY2012. |
DaysPerMonth | Optional | Double | The default number of work days per month. |
Return value
Boolean
Remarks
If an argument is omitted, the default value is specified by the setting on the Schedule tab of the Project Options dialog box.
Using the OptionsCalendar method without specifying any arguments displays the Project Options dialog box with the General tab selected.
Example
The following example sets the first month of the fiscal year to April, default number of work hours per day to 4 hours and default number of work hours per week to 20 hours.
Sub Options_Calendar()
Dim HoursDay As Double
Dim HoursWeek As Double
HoursDay = 4
HoursWeek = 20
OptionsCalendar StartYearIn:=pjApril, HoursPerDay:=HoursDay, HoursPerWeek:=HoursWeek
End Sub