Application.ProjectBeforeSaveBaseline event (Project)
Occurs before a baseline is saved. Uses the EventInfo object parameter.
Syntax
expression. ProjectBeforeSaveBaseline
( _pj_
, _Interim_
, _bl_
, _InterimCopy_
, _InterimInto_
, _AllTasks_
, _RollupToSummaryTasks_
, _RollupFromSubtasks_
, _Info_
)
expression A variable that represents an Application object.
Parameters
Name | Required/Optional | Data type | Description |
---|---|---|---|
pj | Required | Project | The project displayed in the window. |
Interim | Required | Boolean | True if saving an interim baseline. False if saving a full baseline. |
bl | Required | PjBaselines | The baseline you are saving. Can be one of the following PjBaselines constants: pjBaseline, pjBaseline1, pjBaseline2, pjBaseline3, pjBaseline4, pjBaseline5, pjBaseline6, pjBaseline7, pjBaseline8, pjBaseline9, or pjBaseline10. |
InterimCopy | Required | PjSaveBaselineFrom | The interim plan being copied from. Can be one of the following PjSaveBaselineFrom constants: pjCopyBaseline, pjCopyBaseline1, pjCopyBaseline2, pjCopyBaseline3, pjCopyBaseline4, pjCopyBaseline5, pjCopyBaseline6, pjCopyBaseline7, pjCopyBaseline8, pjCopyBaseline9, pjCopyBaseline10, pjCopyCurrent, pjCopyStart_Finish1, pjCopyStart_Finish2, pjCopyStart_Finish3, pjCopyStart_Finish4, pjCopyStart_Finish5, pjCopyStart_Finish6, pjCopyStart_Finish7, pjCopyStart_Finish8, pjCopyStart_Finish9, or pjCopyStart_Finish10. |
InterimInto | Required | PjSaveBaselineTo | The interim plan to which you are saving. Can be one of the following PjSaveBaselineTo constants: pjIntoBaseline, pjIntoBaseline1, pjIntoBaseline2, pjIntoBaseline3, pjIntoBaseline4, pjIntoBaseline5, pjIntoBaseline6, pjIntoBaseline7, pjIntoBaseline8, pjIntoBaseline9, pjIntoBaseline10, pjIntoStart_Finish1, pjIntoStart_Finish2, pjIntoStart_Finish3, pjIntoStart_Finish4, pjIntoStart_Finish5, pjIntoStart_Finish6, pjIntoStart_Finish7, pjIntoStart_Finish8, pjIntoStart_Finish9, or pjIntoStart_Finish10. |
AllTasks | Required | Boolean | True if saving the entire project. |
RollupToSummaryTasks | Required | Boolean | True if you wish to roll up baselines to summary tasks. |
RollupFromSubtasks | Required | Boolean | True if you wish to roll up baselines from subtasks. |
Info | Required | EventInfo | EventInfo.Cancel is False when the event occurs. If the event procedure sets this argument to True, the baseline is not saved. |
Return value
Nothing
Remarks
Project events don't occur when the project is embedded in another document or application.