Application.ResourceAssignment method (Project)

Assigns, removes, or replaces the resources of the selected tasks, or changes the number of units for a resource.

Syntax

expression.ResourceAssignment (Resources, Operation, With)

expression A variable that represents an Application object.

Parameters

Name Required/Optional Data type Description
Resources Optional String The names of the resources to be assigned, removed, or replaced in the selected tasks.

Note Project will not assign a resource if thousands separators or decimal separators are included in the unit values.
Operation Optional Long If Operation is omitted, Project assigns the resources to the selected tasks. The default value is pjAssign. Can be one of the PjResAssignOperation constants.
With Optional String When used with the pjReplace constant for Operation, specifies the names of the resources that replace the resources of the selected tasks.

PjResAssignOperation constants

Constant Description
pjAssign Assigns the specified resources to the selected tasks.
pjRemove Removes the specified resources from the selected tasks.
pjReplace The resources specified by With replace the resources specified by Resources.
pjChange Changes the resource units for the specified resource. This constant can be used only for a single resource.

Return value

Boolean

Remarks

Use the Resources parameter to specify that a resource assignment is requested or demanded when using the Resource Substitution Wizard. For example, the following macro specifies that the assignment of r1 to the selected task is a requested assignment.

Sub RequestAssignment()
    ResourceAssignment Resources:="r1[100%, R]", Operation:=pjChange, With:="" 
End Sub

Note

When using the Resources parameter in this way, D specifies "Demand," R specifies "Request," and N specifies "None." In addition, spaces are not allowed between the units value and the Request/Demand value. For example, Resources:="100%,R" works, but Resources:="100%, R" does not.

The Resource Substitution Wizard cannot substitute material resources. Therefore, you cannot request or demand a material resource for a particular assignment by using the Resources parameter.

Example

The following example prompts the user for the name of a resource, and then assigns that resource to the selected tasks.

Sub AssignResourceToSelectedTasks() 
 
    Dim Entry As String     ' The name of the resource to add to selected tasks 
    Dim R As Resource       ' Resource object used in For Each...Next loop 
    Dim Found As Boolean    ' Whether or not the resource is in the active project 
 
    Entry = InputBox$("Enter the name of the resource you want to add to the selected tasks.") 
     
    ' Assume resource doesn't exist in the active project. 
    Found = False 
 
    ' Look for the resource. 
    For Each R In ActiveProject.Resources 
        If Entry = R.Name Then Found = True 
    Next R 
 
    ' If the resource is found, then assign it to selected tasks. 
    If Found Then 
        ResourceAssignment Resources:=Entry, Operation:=pjAssign 
    ' Otherwise, tell user the resource doesn't exist. 
    Else 
        MsgBox ("There is no resource in the active project named " & Entry & ".") 
    End If 
     
End Sub