Application.SelectTPTask method (Project)
Selects the specified task in the Team Planner view.
Syntax
expression. SelectTPTask
( _TaskUniqueID_
)
expression An expression that returns an Application object.
Parameters
Name | Required/Optional | Data type | Description |
---|---|---|---|
TaskUniqueID | Optional | Variant | Unique ID of the task to select. |
Return value
Boolean
Remarks
If the Team Planner view is not open, the SelectTPTask method generates run-time error 1100, "The method is not available in this situation."
Example
The following example selects two tasks in the Team Planner view. Task 5 remains selected after task 7 is selected.
Sub SelectTwoTasks()
SelectTPTask (5)
SelectTPTask (7)
End Sub