Application.SetTaskField method (Project)
Sets the value of a task field specified by the name of the field.
Syntax
expression. SetTaskField
( _Field_
, _Value_
, _AllSelectedTasks_
, _Create_
, _TaskID_
, _ProjectName_
)
expression A variable that represents an Application object.
Parameters
Name | Required/Optional | Data type | Description |
---|---|---|---|
Field | Required | String | The name of the task field to set. |
Value | Required | String | The value of the task field. |
AllSelectedTasks | Optional | Boolean | True if the value of the field is set for all selected tasks. False if the value is set for the active task. The default value is False. |
Create | Optional | Boolean | True if Project creates a task when the active cell is on an empty row. The default value is True. |
TaskID | Optional | Long | The identification number of the task containing the field to set. If AllSelectedTasks is True, TaskID is ignored. |
ProjectName | Optional | String | If the active project is a consolidated project, specifies the name of the project for the task specified by TaskID. If TaskID is not specified, ProjectName is ignored. The default value is the name of the active project. |
Return value
Boolean
Remarks
To set a task field by ID, use the SetTaskFieldByID method.
Example
The following example changes the task field "Name" of Task ID 3 to "New Task Name", and then changes it back to the original name.
Sub Set_TaskField()
Dim T As Task
Set T = ActiveProject.Tasks(3)
' Save the task name
OldName = T.GetField(pjTaskName)
ViewApply Name:="&Gantt Chart"
SetTaskField Field:="Name", Value:="New Task's Name", TaskID:=3
SetTaskField Field:="Name", Value:=OldName, TaskID:=3
End Sub