PjProjectUpdate enumeration (Project)
Contains constants that specify the action to take with the specified tasks.
Name | Value | Description |
---|---|---|
pj0or100Percent | 0 | Sets only the Actual Start and Actual Finish dates. |
pj0to100Percent | 1 | Sets the percent complete to reflect the update date. |
pjReschedule | 2 | Schedules the remainder of the work to start on the update date. |
Support and feedback
Have questions or feedback about Office VBA or this documentation? Please see Office VBA support and feedback for guidance about the ways you can receive support and provide feedback.