PJTaskOutlineShowLevel enumeration (Project)
Contains constants that specify the task outline levels to display.
Name | Value | Description |
---|---|---|
pjTaskOutlineShowLevel1 | 1 | Display level 1. |
pjTaskOutlineShowLevel2 | 2 | Display levels 1 and 2. |
pjTaskOutlineShowLevel3 | 3 | Display levels 1 through 3. |
pjTaskOutlineShowLevel4 | 4 | Display levels 1 through 4. |
pjTaskOutlineShowLevel5 | 5 | Display levels 1 through 5. |
pjTaskOutlineShowLevel6 | 6 | Display levels 1 through 6. |
pjTaskOutlineShowLevel7 | 7 | Display levels 1 through 7. |
pjTaskOutlineShowLevel8 | 8 | Display levels 1 through 8. |
pjTaskOutlineShowLevel9 | 9 | Display levels 1 through 9. |
pjTaskOutlineShowLevelMax | 65535 | Display all levels. |