Project.LevelToDate property (Project)
Gets or sets the ending date of a range in which overallocated resources are leveled. The default is the project finish date or the last entered date value. Read/write Variant.
Syntax
expression. LevelToDate
expression A variable that represents a Project object.
Remarks
You can also set the LevelToDate property in the Resource Leveling dialog box. To access the setting, click Leveling Options on the Resource tab of the Ribbon, and then click the Level option and set the To date.
Example
The following example lets the user change the date range where leveling occurs, if the current range starts on the project start date or finishes on the project finish date.
Sub ChangeLevelingDates()
Dim Response As Long
Dim NewFrom As Variant, NewTo As Variant
With ActiveProject
If Application.DateDifference(.ProjectSummaryTask.Start, .LevelFromDate) = 0 Then
Response = MsgBox("Overallocated resources are leveled from " & _
"the project start date. Should that be changed?", vbYesNo)
If Response = vbYes Then
NewFrom = InputBox("Date to level from: ")
.LevelFromDate = NewFrom
Else
MsgBox "Resources remain leveled from the project start date."
End If
End If
If Application.DateDifference(.ProjectSummaryTask.Finish, .LevelToDate) = 0 Then
Response = MsgBox("Overallocated resources are leveled to " & _
"the project finish date. Should that be changed?", vbYesNo)
If Response = vbYes Then
NewTo = InputBox("Date to level to: ")
.LevelToDate = NewTo
Else
MsgBox "Resources remain leveled to the project finish date."
End If
End If
End With
End Sub