Task.Baseline7FinishText property (Project)
Gets or sets a string representation of the baseline finish date of a task. Read/write String.
Syntax
expression. Baseline7FinishText
expression An expression that returns a Task object.
Remarks
The Baseline7FinishText property is used for manually scheduled tasks. When you convert a manually scheduled task to an auto-scheduled task, if Baseline7FinishText has any value, you should convert the value to a date for the Baseline7Finish property.
Support and feedback
Have questions or feedback about Office VBA or this documentation? Please see Office VBA support and feedback for guidance about the ways you can receive support and provide feedback.