View settings
You can define various settings for the current process view on the View settings screen.
The screen consists of four tabs:
General settings
Duration settings
Activity label
Calendar settings
General settings
The General settings tab allows you to define the duration format to be used for the current view. The global settings of the duration format used for all new processes and views can be defined in Settings > Options > General.
To learn more, go to Settings.
Duration settings
The Duration settings tab allows you to select the maximum unit of time to be displayed. For example, if you select Day, all the larger units of time (for example, weeks, months, and years) will be converted into days while all the smaller units (hours, minutes, seconds, and milliseconds) will display normally based on the time format precision setting.
Since the length of months and years vary, they are converted to days using their average length:
1 month = 30.436875 days
1 year = 365.2425 days
Use the Time format precision dropdown menu to define how many time units will displayedFor example, when you select Year in the Max time unit dropdown menu, and then select 2 in the Time format precision, only years and months will display. If you select 3, years, months, and weeks will display.
Note
The values of the units that aren't displayed aren't converted into larger ones but are completely omitted. For example, 15 days will display as 2 weeks and not 2.07 weeks.
The Show duration in working hourscheckbox automatically sets the max time unit to "hour" and time format precision to "unlimited".
Activity label
The Activity label tab allows you to do the following:
Set the default activity label.
Select the display format (Activity, Label, or Custom)
(If the default label is Custom) Edit the display format.
Calendar settings
Select an existing calendar in the Calendar dropdown menu. If the menu options don't include the calendar template that you want to use, select the ellipses (...) to define a new template. If an existing calendar is close to what you want, select it in the Calendar dropdown menu, and then select (...) > Edit.
Calendar templates can be shared across Power Automate Process Mining projects. To manage all calendar templates, select Settings > Working hours. To learn more, go to Settings.