ProjectDataSet.ProjectRow.PROJ_OPT_SPREAD_PCT_COMP Property
Indicates whether percent complete is spread to the status date or to the task finish date.
Namespace: [Statusing Web service]
Service reference: http://ServerName:32843/[Project Service Application GUID]/PSI/Statusing.svc
Web service reference: http://ServerName/ProjectServerName/_vti_bin/PSI/Statusing.asmx?wsdl
Syntax
'Declaration
Public Property PROJ_OPT_SPREAD_PCT_COMP As Boolean
Get
Set
'Usage
Dim instance As ProjectDataSet.ProjectRow
Dim value As Boolean
value = instance.PROJ_OPT_SPREAD_PCT_COMP
instance.PROJ_OPT_SPREAD_PCT_COMP = value
public bool PROJ_OPT_SPREAD_PCT_COMP { get; set; }
Property Value
Type: System.Boolean
True if percent complete is spread to the status date.
Remarks
True if percent complete is spread to the status date; otherwise, false. PROJ_OPT_SPREAD_PCT_COMP maps to the Edits to total task % complete will be spread to the status date option on the Calculation tab of the Options dialog box in Project Professional.
The default value for new projects is determined by the enterprise global template. If there is no enterprise global template value, the default value is false.