Add or remove a timesheet task (line) (Project Server 2010)
Applies to: Project Server 2010
Topic Last Modified: 2011-04-13
Each line on your timesheet captures your actual work for the selected reporting period. You can add lines for different categories of time that you want to capture, or you can remove a line if you no longer have any time to report on the task.
Add a task to your timesheet
On the Quick Launch, under My Work, click Timesheet.
On the Tasks tab of the ribbon, in the Tasks group, click the arrow under Insert Row.
Choose how you want to add a task:
Insert Task Assign yourself to an existing task, and then add that task to your timesheet.
Create a New Task Create a new task within an existing project, and then add that task to your timesheet.
Add Yourself to a Task Add one of your assigned tasks to your current timesheet.
Insert Team Tasks Assign yourself to one of your team tasks, and add that task to your timesheet.
Insert Administrative Task Add sick leave, vacation, training, travel, or any other non-project time to your timesheet.
Insert Personal Task Add a task that lets you capture any other time on your timesheet.
Remove a task from your timesheet
On the Quick Launch, under My Work, click Timesheet.
Click the check box to the left of the task that you want to remove, and then, on the Tasks tab, in the Tasks group, click Remove Task.