Exercise - Create and schedule kanbans for subcontracting
Note
Before you begin this exercise, you must have completed the previous exercise, Create an activity-based subcontracting rule.
Prerequisite
You must set up unit conversion in the demo data to be able to perform this exercise.
- Go to Product information management > Products > Released products.
- Filter the list to select the product L0001.
- On the Product FastTab, select Unit conversions from the Set up group.
- Place your cursor on Inter-class conversions.
- Select New.
- In the From unit, select hr; in the To unit, select ea.
- Select OK.
- Close the form, and then close the Released product details page.
Scenario
In this exercise you will create and schedule kanbans for subcontracting.
- Go to Product information management > Lean manufacturing > Kanban rules.
- Select New.
- In the First plan activity field, enter or select GTL-Subcontracting activity.
- Select the Multiple activities check box.
- In the Last plan activity field, enter or select GTL-Transfer to subcontractor.
- On the Choose Kanban flow page, select Generate flows.
- Select OK.
- Expand the Details FastTab.
- In the Product field, enter L0001.
- Expand the Quantities section.
- Set Default quantity to 50.00.
- In the Fixed kanban quantity field, enter 25.
- Select Save.
- Expand the Kanbans FastTab.
- Select Add.
- In the Number of new kanbans field, enter 1.
- Select Create.
- Select Details.
- Expand the Jobs section.
- View jobs for process and transfer to a subcontractor.
- Close all pages.
- Go to Production control > Kanban > Kanban job scheduling.
- In the Work cell field, select eBookSub.
- In the list, select the first row.
- Select Schedule from date to open the drop-down dialog box.
- Select Schedule.
- Close all pages.