Exercise - Create a Work order cost control report
Management in the Munson's Pickles and Preserves Farm has requested a report of the work order costs that are consumed over the entire year of 2019. Your task is to create that report as follows:
- Go to Asset management > Inquiries > Work orders > Work order cost control.
- In the Work order cost control dialog box, in the From date field, enter 1 January 2019.
- In the To date field, enter 31 December 2019.
- Select a Financial dimension set that you want included in the calculation, for example, Service line.
- Keep the Level field set to 0.
- Select Yes on the Show open committed cost toggle button to include open committed costs in the calculation.
- Select OK to start the calculation.