You're creating a new event kanban rule and need to define when the last job of a kanban is completed. The material handling units are automatically registered as empty. Which one of the following options should you select?
When the source requirement is registered
When handling units are received
Manual - includes scanning empty
You're creating a new event kanban rule and need to define when the products that are supplied by event kanbans are consumed by the demand source. The material handling units are automatically registered as empty. Which one of the following options should you choose?
You're creating a new event kanban rule and need to define the material handling units, which must be explicitly registered as empty. Which one of the following options should you choose?